Approvals & Communication

How to Get Client Approval for Interior Designs and Material Selections

How to submit designs and material choices room by room, handle revisions, preserve approved versions and keep an approval history you can rely on.

Nothing creates more rework than building something the client has not truly approved. Yet approvals are often the loosest part of interior projects: a render in a WhatsApp group, a "looks good" two days later, a revised version the client never saw. This guide sets out a process that gets decisions faster and leaves a record you can trust.

Why approvals fail

  • The request is vague: "Please check and let me know."
  • Too many decisions arrive at once, so the client postpones all of them.
  • Versions get mixed, and the client approves something different from what you build.
  • Approval is verbal or buried in chat.
  • Site staff are not told what changed.

Step 1: Submit layouts and 3D renders properly

Present layouts before renders, because a plan is cheaper to change. Give every file a title with room and version, for example "Living and dining, layout v2". Include a short note stating what you are asking the client to decide and by when. Attach only what is needed for that decision.

Step 2: Work room by room

Split the project into rooms or zones: living and dining, kitchen, master bedroom, children's room, pooja, bathrooms. Ask for approval of each separately. This lets work in finished decisions begin while others remain open, and prevents one disagreement blocking the whole project.

Step 3: Handle material and finish selection

For each material decision, present the options with the following information:

  • Photo or sample reference, brand, code and finish.
  • Where it will be used.
  • Cost implication versus the allowance in the quotation.
  • Lead time, if it affects the schedule.

Ask the client to choose one and confirm. For colour-critical items such as laminates, stone and paint, suggest viewing physical samples in natural light before final approval. Record the decision per room and item.

Step 4: Record client comments

When a client comments, capture the exact words and attach them to the version they refer to. "Make the TV wall warmer" refers to a specific render, and you will want that link later. Paraphrase gently in your reply, to check you understood, and record the outcome.

Step 5: Control versions

  • Every revision gets a new version number.
  • Only one version per item is marked approved.
  • Older versions are marked superseded, not deleted.
  • File names carry room, item and version.

Step 6: Set approval deadlines

Deadlines are not rude; they are part of the schedule. "To keep the laminate order on time for 20 March, I need your decision by 12 March." Link each deadline to a consequence the client cares about, such as the possession date.

Step 7: Handle requested revisions

Treat a request for changes as a normal step, not a failure. Acknowledge it, state the effect on cost and timing if any, issue a new version and say what changed. If the revision adds cost, raise it as a priced change request (see handling extra work) before work begins.

Step 8: Preserve approved versions and tell the site

Once approved, treat the version as the build reference. Share it with the site supervisor and relevant vendors, and make sure earlier versions are not still circulating. A weekly check ("Which drawing version is each trade working from?") catches most errors before they cost money.

Step 9: Keep an auditable approval history

For each approval, you should be able to answer:

  • What exactly was approved (item and version)?
  • Who approved it?
  • When?
  • What comments or conditions came with it?

A design approval checklist

  • Request names the room, item and version
  • Request states exactly what the client must decide
  • A decision date is given with the reason
  • Cost and schedule effects are stated
  • Client decision is recorded with date and name
  • Comments are saved against the version
  • Superseded versions are marked and withdrawn
  • Approved version is shared with site staff and vendors
  • Material selections list brand, code and finish
  • Physical samples seen for colour-critical items
  • Price-affecting changes are raised as change requests

Example (illustrative)

A designer in Mumbai submits the master bedroom: layout v1 (approved), render v2 (changes requested: "headboard panel in darker wood"), render v3 (approved on 9 March). Laminate options A and B are shown with brand and code; the client chooses B on 10 March. The designer sends the supervisor the approved render v3 and the finish list, and marks v1 and v2 superseded.

Where software helps

Design approval software and material selection approvals in InterioDesk handle the mechanics: submission per room, client decisions in a browser portal, version status and a history. See the sign-off record use case for how quotations, designs, materials and changes combine in one timeline.

Common mistakes

  • Asking for approval of everything at once.
  • Accepting an ambiguous reply as approval.
  • Not marking old versions superseded.
  • Telling the client but not the site.
  • Ignoring the cost effect of revisions.

Wording that gets answers

The way you ask often decides how fast you are answered. Compare these two requests.

  • Weak: "Please check the attached and let me know your thoughts."
  • Strong: "Attached: living room render v2 (TV wall in walnut, warm cove lighting). Please approve it or tell me what to change by Thursday 12 March so the carpentry order is placed on time."

The strong request names the item and version, states the decision, gives a date and explains why the date matters. It is also easy to answer in one line.

Handling families with several decision-makers

  • Ask at kickoff who has the final say, and say it back in writing.
  • Invite others to comment but not necessarily to approve.
  • If two people disagree, pause the item and summarise both views neutrally; do not choose a side.
  • Record who approved each item, so later disagreements about "who decided" are factual.

When approval is delayed

Delays are normal; silence is not. Follow up once after two days, then again with the consequence: "If I do not hear by Thursday, the laminate order moves to next week's batch, which delays carpentry by about five days." If a client is still silent, call, then record the outcome. Never assume silence means yes unless your agreement explicitly says so, and have that wording reviewed by a lawyer.

Approvals across the project life

StageWhat is approvedWho needs the result
ConceptLayout and design directionDesigner, client
QuotationScope and priceDesigner, client, accounts
DetailingWorking drawings and finishesSupervisor, carpenter, vendors
ExecutionChanges and extrasSupervisor, accounts
HandoverCompletion and snag closureDesigner, client

Seeing approvals across the whole life of the project helps you plan the asks, rather than reacting to them.

Presenting designs so clients can decide

Approvals are quicker when the material you present is easy to judge. A few habits help most.

  • Show before and after in context. Place the render next to a photo of the existing room when you can, so the client sees the change.
  • Annotate. Add short callouts such as "walnut veneer", "warm 2700K cove light" and "storage behind sliding door".
  • Limit to what is decidable. One view per decision is better than six views of the same thing.
  • Say what is not decided yet. If the curtains and loose furniture are not finalised, mark them so the client does not expect them to be shown.
  • Offer a walk-through call for the first major approval, and written approval afterwards.

Material boards that work

Group materials by room and by relationship: floor, wall, shutter and counter that sit together. Present two good combinations rather than ten individual swatches, and note the price effect of each combination against the allowance. Where a finish is a very different cost, say so clearly: clients forgive a high price they were warned about but not one they discover later.

Approval deadlines for the schedule

DecisionLatest decision date (relative to work)Why
Layout and electrical pointsBefore civil and electrical startPoints are expensive to move after chasing
Tile and sanitarywareBefore wet-area workFixing levels depend on the product
Carpentry finishesBefore carcass ordersLead time for laminates and veneers
Paint shadesBefore painting startsTinting and sample patches take time
Hardware and fittingsBefore carcass fabricationHardware dictates internal dimensions

Recording an approval you received on a call

It happens: the client approves on the phone. Within the hour, write it down and send it back: "Confirming our call today: you approved living room render v3 with the walnut TV wall. Please reply 'confirmed' if that is correct." A one-word reply turns a spoken approval into a record.

Approval scenarios and how to respond

ScenarioWhat to do
The client approves, then a relative objectsPause only the affected item, restate what was approved and when, and ask the decision-maker to confirm or revise in writing.
The client approves a render but dislikes the real finishCompare the approved selection (code, sample) with what was installed. If it matches, offer a priced alternative; if not, correct it at your cost.
The client keeps requesting small revisionsAgree a number of revision rounds up front. After that, quote additional design time.
The client is travelling and unreachableMove non-dependent work forward, and state the date after which the schedule will slip.
Two versions are in circulationStop work on the affected item, confirm the approved version with the client and recall the other.

Limiting revision rounds fairly

Unlimited revisions are a hidden cost. State in your quotation how many rounds of design revision are included, and what additional rounds cost. Most clients accept this when it is explained at the start, and it encourages them to give consolidated, thoughtful feedback.

Approval metrics worth tracking

Note how many days each client takes to respond, how many revisions each room needs and which decisions cause most delay. After a few projects you will see patterns, such as kitchens always needing three rounds, and can plan time and fees accordingly.

Conclusion

Approvals work when they are specific, staged, versioned and recorded. Ask one clear question at a time, give a date, keep only one approved version per item, and tell the site. Your reward is less rework, calmer client relationships and a record that settles disagreements quickly. The next article shows how to keep clients informed during execution: sharing site progress updates.

General guidance, not legal advice. Whether a recorded approval has legal effect depends on your contract.

Collect approvals with a clear historySubmit layouts, renders and materials to the InterioDesk client portal and keep every decision tied to a version. Start a free trial →

General guidance only. This article is not legal, tax or contractual advice. Speak to a qualified professional about your own agreements and GST position.

Topics: approvals, design review, materials

Frequently asked questions

How many design options should I present?

Two when the layout genuinely allows a choice; one well-argued option when it does not. More options usually slow decisions.

How do I get clients to decide faster?

Ask a specific question, give a date, and explain the consequence of delay on the schedule.

What if a client approves and then changes their mind?

Treat it as a revision. If it affects cost or timing, raise a change request.

Is a WhatsApp "OK" an approval?

It is better than nothing, but it is easy to misread. Prefer an approval that identifies the version.

Should I approve materials from screens?

Screens distort colour. For colour-critical finishes, ask clients to see physical samples.

How should I tell site staff about approved changes?

Give them access to the approved version, and remove or mark superseded drawings.

What is version control for designs?

A simple discipline: every revision gets a new version number, and only one version is marked approved.

How long should I keep approval records?

At least through handover and any defect-liability period in your contract. Check with your lawyer.

Can clients approve different rooms at different times?

Yes. Room-by-room approval keeps the project moving.

Collect approvals with a clear history

Submit layouts, renders and materials to the InterioDesk client portal and keep every decision tied to a version.