The problem: overruns found at the end
A profitable-looking project can quietly lose money. The client adds two wardrobes. The vendor raises a rate. Plywood is bought twice after a wrong measurement. Because nothing is tracked against the agreement, the designer discovers the real picture at final settlement, when nothing can be changed.
The seven numbers
| Figure | What it tells you |
|---|---|
| Original contract value | What the client first agreed to. Preserved. |
| Approved additional charges | Approved change requests added to the contract. |
| Current approved contract value | Original plus approved additions. The most the client owes. |
| Actual project costs | What you have spent so far. |
| Estimated final cost | Your forecast of total cost on completion. |
| Payments received | Recorded payments from the client. |
| Outstanding client balance | Current approved value minus payments received. |
Keeping these apart prevents a common confusion: a high payments-received figure does not mean the project is profitable, and a low one does not mean it is losing money.
How the workflow operates
- Fix the baselineRecord the approved quotation as the original contract value.
- Revise through approvalsAdd extras as change requests. Approved ones move into the current approved value.
- Record costsEnter actual costs as they happen and keep the estimated final cost current.
- CompareLook at estimated final cost against current approved value to see margin and risk.
- Act earlyIf forecast cost climbs, talk to the client about a change, reduce scope or renegotiate vendors while there is time.
Example: a Chennai flat (illustrative)
| Original contract value | ₹14,00,000 |
| Approved additions (study room, extra storage) | + ₹1,60,000 |
| Current approved contract value | ₹15,60,000 |
| Actual costs to date | ₹9,10,000 |
| Estimated final cost | ₹13,20,000 |
| Payments received | ₹10,00,000 |
| Outstanding client balance | ₹5,60,000 |
These figures are examples, not market rates. The designer can see an expected margin of ₹2,40,000 before any new surprises, and a clear amount still to collect.
Scope and limits
- This is project-level budget tracking, not bookkeeping, tax filing or GST reporting.
- Accuracy depends on you recording costs and updating the forecast.
- InterioDesk does not set your rates or margins.