The problem: extras that are done first and discussed later
Scope changes are normal. A client sees the finished carcass and wants a loft above the wardrobe. A new fridge needs a bigger niche. A family member asks for a pooja unit. The issue is not the change, but the habit of saying "sure, we will adjust" and settling the price at the end, when the client remembers a different number.
What change order management does
InterioDesk separates the original agreement from everything that follows. Every extra is a change request with a description, price, reason and status.
- Pending. Submitted, awaiting the client's decision. Does not change the contract value.
- Approved. Accepted by the client. Added to the current approved contract value.
- Rejected. Declined, kept for reference, no effect on the contract.
Because the baseline never moves, you can always explain the current total as: original agreement plus approved changes.
How the workflow operates
- Capture the requestLog it the moment the client asks, with room, description and any photos.
- Price itAdd the additional charge and note any timeline effect.
- SubmitThe client reviews it in the portal and approves or rejects.
- ReviseOn approval, the revised contract value and balance update.
- ExecuteSite staff work to the approved scope.
Practical benefits
- Fewer disputes about what was promised.
- Extras are paid for because they are priced before they are built.
- Clients see exactly why the total has changed.
- Pending requests are visible, so none is forgotten.
Example: a Pune villa
The original agreement is ₹12,00,000. The client asks for an extra wardrobe in the guest room (₹68,000) and a wall panel in the foyer (₹35,000). The wardrobe is approved; the foyer panel is rejected after the client sees the price. The revised contract value becomes ₹12,68,000. The rejected request remains on record. (Illustrative figures.)
Scope and limits
- Change requests record commercial agreement inside the project. Your written contract still governs legal rights.
- InterioDesk does not decide pricing for you.
- It is most effective when the team agrees not to start extra work before it is approved.
Related reading
Use the template in how to handle extra work and scope changes, then see the effect on the budget in budget management.