Payments & Handover

Interior Design Project Handover Checklist for Indian Homes

How to hand over an Indian home interior cleanly: inspection, snag list, walkthrough, warranties, final drawings, payments and acknowledgement, with a printable checklist.

Handover is the moment a project becomes the client's home. A rushed, unstructured handover produces a trail of "one more thing" calls, disputed defects and unpaid balances. A structured one ends the project cleanly and gives you a reference for any future question. This guide gives you the process and a detailed checklist for Indian home interiors.

The handover sequence

  1. Internal final inspectionYou and your supervisor inspect every room before the client sees it.
  2. Fix, then re-inspectResolve obvious defects, clean the site and photograph completion.
  3. Client walkthroughWalk each room together, recording observations.
  4. Snag listAgree what remains, with dates.
  5. Document handoverProvide warranties, drawings, manuals and codes.
  6. AccountsConfirm the final contract value, payments and the balance.
  7. AcknowledgementSign the handover record.

Final inspection

Inspect with the same eye the client will use, in daylight and with lights on, standing where they will stand. Open every door and drawer, run every tap and switch every light. Do this at least a day before the walkthrough.

Outstanding work and snags

Record every defect with a location, a photo, a description and an owner. Group by trade so each vendor gets one clear list. Typical snags include uneven laminate edges, misaligned shutters, paint touch-ups, silicone gaps, hardware that binds, scratched glass and loose switch plates.

Snag list format

#LocationDefectTradePhotoTarget dateStatus
1Master bedroom wardrobeRight shutter misalignedCarpenterYes Open
2KitchenGap in silicone near sinkFitterYes Open

Client walkthrough

Schedule enough time for a calm walkthrough, usually an hour or more for a three-bedroom flat. Walk in the same order as the checklist below, ask the client to note anything they see, and add it to the snag list. Explain care instructions as you go: how to clean laminate, how to operate soft-close hardware, which switch controls which light.

Printable room-by-room checklist

Handover checklist

Project: ____________ Date: ________ Inspected by: ____________

General (all rooms)

  • Work matches approved drawings and finish list
  • Walls and ceilings: paint finish even, no patches or drips
  • Floors clean; skirting fixed; no hollow or cracked tiles
  • Doors and windows open, close and lock smoothly
  • All switches, sockets and lights work; plates fixed and clean
  • Fans, AC provisions and drainage points work
  • No exposed wires; MCB labels correct
  • Room cleaned; debris removed

Kitchen

  • Shutters aligned; soft-close and hinges working
  • Drawers and baskets slide smoothly
  • Countertop edges and joints finished; silicone neat
  • Sink, tap and drainage tested; no leaks
  • Chimney, hob and appliances installed and working
  • Backsplash and grout clean

Bedrooms

  • Wardrobe shutters, hinges, channels and handles aligned
  • Loft doors, shelves and hanging rods fixed
  • Bed, headboard and back panels secure
  • Lighting scenes and bedside points tested
  • Mirrors fixed and unscratched

Living and dining

  • TV unit, back panel and cable routing neat
  • False ceiling joints finished; cove lights even
  • Wall panelling and finishes consistent
  • Furniture installed and level

Bathrooms

  • Taps, showers and fixtures tested; no leaks
  • Drains flow freely; slope toward drain
  • Tile joints grouted; silicone sealed
  • Geyser, exhaust and lights working
  • Glass and hardware undamaged

Material and finish checks

  • Laminates, paints and tiles match approved codes
  • Spare tiles, laminates or hardware set aside, if supplied
  • Paint codes and finish list recorded for touch-ups

Fixtures and hardware

  • Handles, hinges, locks and channels tight and smooth
  • Door stoppers, hooks and rails installed
  • Keys counted and handed over; spare keys labelled

Manuals, warranties and documents

  • Warranty cards and invoices: chimney, hob, geyser, lights, hardware
  • User manuals and care instructions
  • Final drawings and electrical/plumbing point layout
  • Contact details of key vendors for warranty claims

Accounts and records

  • Original contract value, approved changes and total confirmed
  • Payments received listed; balance stated
  • Final payment arrangement agreed
  • Completion photographs of every room taken and stored
  • Snag list signed with dates
  • Client acknowledgement signed

A compact one-page signature form is available on our handover sign-off sheet.

Materials and finishes checks in practice

Match what is installed against the approved material list, not against memory. Check batch consistency in tiles and laminates, since a different batch can show a slightly different shade. Note codes and brands so a damaged piece can be replaced years later.

Fixtures and hardware

Test hardware under real use, not just a quick open and close. Open every drawer fully, load a shelf slightly, close shutters from different angles. Many complaints arrive months later about the exact hinge or channel you did not test.

Manuals, warranties and final documents

Collect these as items are installed rather than on handover day. Hand them over in a labelled folder, and keep a digital copy filed against the project. Project document management in InterioDesk is designed for this: documents filed per project and shareable with the client.

Outstanding payments

Handover usually coincides with the last milestone. Prepare a one-page statement showing the original contract value, approved changes, current value, payments received and balance. Explain it in the walkthrough, and agree how and when the balance will be paid. See payments and milestones. Separate new requests from genuine defects: defects go on the snag list; new requests are priced changes.

Completion photographs and handover records

Photograph every room in its finished state, with the date. These images protect both sides if a later damage claim arises. Store them with the signed acknowledgement, the snag list and the final accounts statement as the project's handover record.

Client acknowledgement

A short signed note that the client has inspected the work and received the listed documents, subject to the snags listed, is common practice. Its legal effect depends on your contract, so have a lawyer review your wording.

Common mistakes

  • Letting the client discover defects before you do.
  • Mixing new requests with defects.
  • Not photographing completion.
  • Collecting warranties after the client has moved in.
  • Handing over without agreeing the final balance.
  • No snag list dates.

Handover day: a suggested running order

TimeActivity
Day beforeFinal clean; internal inspection; photograph every room; prepare the document folder and account statement
0:00-0:15Welcome; confirm what will be covered; hand over keys
0:15-1:15Room-by-room walkthrough; demonstrate hardware and appliances; note snags with photos
1:15-1:30Review the snag list; agree target dates
1:30-1:45Hand over documents and warranties; explain care instructions
1:45-2:00Account statement; final payment arrangements; sign acknowledgement

Common snags in Indian homes

  • Hairline gaps at laminate edges and between wall panels.
  • Shutters out of alignment after hardware settles.
  • Paint touch-ups near switch plates and at skirting.
  • Silicone gaps in kitchens and bathrooms.
  • Tile hollowness found by tapping, especially in wet areas.
  • Switches or lights wired to the wrong circuit.
  • Door stoppers, hooks and rails missing from the final fit-out.

After handover

Keep a short follow-up routine: contact the client after one week to check how the home is working, close any remaining snags by the agreed dates and share the final folder. Clients remember how a project ended, and an organised finish is the strongest foundation for referrals, which are the lifeblood of most design practices.

Preparing the home for the client

The handover is the client's first experience of the finished home, so small details carry large weight.

  • Deep clean of all rooms, including inside cabinets and drawers
  • Protective films removed from glass, appliances and hardware
  • Labels and stickers removed; stray adhesive cleaned
  • Switchboards, MCBs and gas connections labelled
  • Water, electricity and lighting working before the client arrives
  • Fresh paint touch-ups done on the day, not weeks before
  • Keys, remote controls and manuals set out for hand-over
  • Fresh flowers or a simple welcome arrangement, if that suits your style

Teaching the client to look after the home

Many later complaints are really care questions. At handover, give a short care sheet: how to clean laminate, stone and glass without damaging them; which cleaners to avoid; how to adjust hinges and drawer channels; what to do about seasonal swelling in timber; and how to report a defect. Suggest simple habits such as wiping spills from laminate edges quickly and keeping wet items off veneer. Clients appreciate guidance, and it protects the finishes you worked hard to deliver.

Defects, warranties and responsibility

Be clear about who handles what after handover: your own workmanship, vendor warranties and appliance brand service. Provide a list of contacts and the purchase details of each warranted item. State how long you will respond to workmanship issues, as your contract provides. If a claim arrives, the handover photographs and snag list show what the home looked like on the day.

Closing the file

  1. Reconcile accountsMatch all payments with the contract value and approved changes; confirm a zero balance or the agreed final date.
  2. Archive documentsStore the final drawings, approvals, change log, snag list, photos and acknowledgement in one project folder.
  3. Ask for feedbackA short call a week later, asking what worked and what did not, improves your next project.
  4. Update your templatesAdd any new snag types to your checklist and any clause gaps to your quotation wording.

Handover for different project types

Project typeExtra items to check
Rental or lease-hold homeLandlord permissions and reinstatement requirements; agreed list of removable items
Apartment in a societySociety handover requirements, deposits, debris clearance and lift protection removed
Independent house or villaExternal finishes, terrace waterproofing and drainage, gate and lighting points
Home officeNetwork points, power backup, ergonomic furniture adjustment
Elderly-friendly homeGrab bars, anti-slip flooring, switch heights, night lighting

Adapt the room-by-room checklist above with the rows that match your project, and keep the adapted version as a template for similar jobs.

Conclusion

A good handover is the last piece of project management and the first piece of your reputation. Inspect first, walk through calmly, record snags with dates, hand over documents, confirm the accounts and sign the acknowledgement. Keep everything in one project record. Combined with the habits in managing a project from start to handover, this makes the end of a project as organised as the beginning.

General guidance for Indian homes, not legal advice. Your contract governs defect liability and warranties.

Keep the handover record with the projectFile warranties, final drawings and acknowledgements against the project in InterioDesk so they are there when the client needs them. Start a free trial →

General guidance only. This article is not legal, tax or contractual advice. Speak to a qualified professional about your own agreements and GST position.

Topics: checklist, handover, snag list

Frequently asked questions

What is a snag list?

A list of defects and unfinished items found during inspection, each with a location, description and target date for fixing.

When should I do the final inspection?

Before the client walkthrough, so you have already fixed the obvious issues.

Should the client sign a handover document?

A signed acknowledgement is good practice. What legal effect it has depends on your contract.

What if the client lists new demands at handover?

Separate real defects from new requests. Defects go on the snag list; new requests become priced change requests.

What documents should I hand over?

Warranty cards, invoices, manuals, final drawings, point layouts, finish codes and care instructions.

When is the final payment due?

As per your agreed milestones. See payments and milestones.

How should I record completion?

Take dated photos of every room in the finished state and store them with the project.

What about defects found after handover?

Follow the defect-liability and warranty terms in your contract. Keep the handover record to show the condition at handover.

Does Indian law require a specific handover form?

This article does not provide legal advice and does not claim any form is mandatory. Check your contract and take legal advice if unsure.

Keep the handover record with the project

File warranties, final drawings and acknowledgements against the project in InterioDesk so they are there when the client needs them.